Minh hoạ Wind inspection

Wind Tower Flange Bolting QC Dossier: Required Records & Torque/Tension Steps

Wind Tower Flange Bolting QC Dossiers are among the most strictly audited packages in onshore and offshore wind projects. Because tower flange joints endure 20–25 years of cyclic fatigue loads, any missing traceability or improper Bolt Torque/Tension record can trigger an immediate NCR.

4 Mandatory Record Groups in Every Bolting Dossier

  • Material Traceability: EN 10204 3.1 MTCs for HV 10.9 bolts/nuts/washers (EN 14399) and OEM-approved lubricant certificates.
  • Tool Calibration: Valid calibration certificates for Hydraulic Torque Wrenches or Bolt Tensioners and pump pressure gauges.
  • Pre- & In-Process Sheets: Flange Gap Inspection record (Feeler Gauge) and signed Torque/Tension Record Sheet per bolt number.
  • Visual Verification: Photos of Witness Marks (Torque Stripe) and thread protrusion checks.

Multi-Pass Tightening & QC Verification

PassField ExecutionQC Documentation
NumberingNumber bolts 1 to N clockwiseFlange map & photo
Pass 1 (30%–50%)Cross-pattern (star) tightening to seat flanges evenlyPump pressure & sign-off
Pass 2 (80%–100%)Sequential tightening per calibrated Pressure-to-Torque chartFull Torque/Tension Record Sheet
100% Check PassFinal verification pass + continuous Torque Stripe across flange, washer, nut, and threadTimestamped inspection photos

Critical Field Rules

  • Never reuse tightened HV 10.9 bolts: Once tensioned to design preload, bolts removed for flange rework must be replaced with new certified sets.
  • Touch-up coating: Clean and inspect flange touch-up areas per ISO 8502-3 dust control before installing bolt caps.